Engineering Manager
PT. Tiara Marga Trakindo (parent company of Trakindo Utama), Jakarta
08.2007 - 01.2011
- Representing company’s management
- Leading owner engineer team
- Assisting procurement dept in tender process
- Managing and monitoring construction cost
- Managing project quality
- Monitoring time schedule
- Managing communication line within stakeholders
- Taking decision in technical matter
- Supervising consultant and contractor activities
- Major completed projects:
- Cipta Krida Bahari New Facility, Samarinda
- Period: Nov. 2010 ~ January 2011
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 34,000,000,000
- General description: 3,000 m2 warehouse + 600 m2 office + 3,000 m2 open yard.
- Gedung Tiara Marga Trakindo (TMT 2), Cilandak, Jakarta
- Period: December 2009 ~ November 2010
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 55,000,000,000
- General description: building 4 storeys + 1 basement, total area 7,000 m2, reinforced concrete, two elevators.
- Interior & Relocation Works of Gedung Tiara Marga Trakindo (TMT 1), Cilandak, Jakarta
- Period: April 2009 ~ January 2010
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 30,000,000,000
- General description: coordinating interior works for 5 companies including moving works.
- Gedung Tiara Marga Trakindo (TMT 1), Jakarta
- Period: January 2008 ~ June 2009
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 214,000,000,000
- General description: building 17 storeys + 2 basement, total area 35,000 m2, reinforced concrete, five elevators.
- Trakindo Utama Office Branch, Pekanbaru
- Period: August 2007 ~ February 2008
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 25,000,000,000
- General description: comprising office, workshop and warehouse, reinforced concrete with steel truss roofing.
- Sanggar Sarana Baja Transporter Facility Extension, Tangerang
- Period: February 2008 ~ June 2008
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 12,500,000,000
- General description: comprising office, workshop, reinforced concrete with steel truss roofing.
- Sanggar Sarana Baja Remanufacturing Facility, Kariangau, Balikpapan
- Period: April 2009 ~ June 2009
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 12,000,000,000
- General description: to convert existing sawmill to become workshop.
- Sanggar Sarana Baja Site Service Facility, Timika, Papua
- Period: September 2008 ~ June 2009
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 30,000,000,000
- General description: nine bays of workshop, equipped with sandblast & paint shop.
- Cipta Krida Bahari New Facility, Balikpapan, East Kalimantan
- Period: September 2008 ~ June 2009
- Scope: Project Management
- Project outline:
- Construction cost: Rp. 12,800,000,000
- General description: 500 m2 office + 1000 m2 workshop + 2000 m2 open yard.
- Company new business process model project
- Period: July 2010 ~ August 2010
- Duties:
- Developing project charter
- Leading team member
- Presenting to Board of Director